RFP-0003 — Contractor Q&A
Point Lakeview Phase 2
Questions and answers from the pre-proposal site visit and written submission period, distributed equally to all pre-qualified contractors.
Proposal deadline: Friday, May 1, 2026 by 5:00 PM
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
RFP-0004 — Contractor Q&A
Konocti Road Below the Gate Phase 1
Questions and answers from the pre-proposal site visit and written submission period, distributed equally to all pre-qualified contractors.
Proposal deadline: Friday, May 8, 2026 by 5:00 PM
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
Minimum typical setup for heavy equipment:
- 300-500 gallon water tank minimum
- Pump capable of ~20–50 GPM
- Hose line attached and ready (not buried in the truck)
- Multiple suppression tools (water + extinguishers + hand tools)
- 500 – 1,000+ gallons staged
- Multiple suppression tools (water + extinguishers + hand tools)
- Sometimes dedicated "fire watch" with water unit
General CalFire standards:
>30% RH — generally safe with mitigation
25–30% RH — proceed cautiously
20–25% RH — expect restrictions / possible shutdown
<20% RH — plan for shutdown
<15% RH — assume no work
RFP-0013 — Contractor Q&A
Panorama Sunrise Fuel Break (CWDG-2)
Questions and answers from the pre-proposal site visit and written submission period, distributed equally to all pre-qualified contractors.
Proposal deadline: Friday, May 15, 2026 by 5:00 PM
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
RFP-0006 — Contractor Q&A
Adamson Ranch Fuel Break Phase 1 (CWDG-1)
Questions and answers from the pre-proposal site visit and written submission period, distributed equally to all pre-qualified contractors.
Proposal deadline: Friday, May 22, 2026 by 5:00 PM
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
RFP-0015 — Contractor Q&A
Wheeler Point (CWDG-2)
Questions and answers from the pre-proposal site visit and written submission period, distributed equally to all pre-qualified contractors.
Proposal deadline: Friday, May 22, 2026 by 5:00 PM
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
RFP-0018 — Contractor Q&A
Meadowood (CWDG-2)
Questions and answers from the pre-proposal site visit and written submission period, distributed equally to all pre-qualified contractors.
Proposal deadline: Friday, May 29, 2026 by 5:00 PM
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
RFP-0019 — Contractor Q&A
Lower Aves Phase 1 (CWDG-2)
Questions and answers from the pre-proposal site visit and written submission period, distributed equally to all pre-qualified contractors.
Proposal deadline: Friday, June 5, 2026 by 5:00 PM
Decision expected: Friday, June 12, 2026
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
Vegetation Treatment (Please refer to the Scope of Work for full treatment plan)
- All grasses should be mowed or cut.
- Chaparral should be cut at the base. Do not pull shrubs; ground disturbance is not permitted.
- Quality native species such as Manzanita, Toyon, and Monkeyflower may be selectively trimmed and retained in accordance with the Scope of Work rather than removed.
- All remaining chaparral should be treated per the Scope of Work.
- Quality trees should be limbed up to ~10 feet.
- All dead and dying trees should be removed. See Scope of Work to determine biowaste treatment.
- Smaller debris: bag using CLERC-provided contractor bags and placed at the front of the site or in an accessible area.
- Larger items: pile along the roadside for City of Clearlake pickup.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are rocky and uneven in places. Use appropriate footwear and exercise caution.
- Falling limbs: Removal of dead and dying trees is part of the project prescription. Be alert to overhead hazards during felling and limbing operations.
- Feral dogs: Wild dog packs have been observed in the area. Stay alert and do not approach.
- Nearby encampments: Encampments are present in the surrounding area. Remain situationally aware and contact Cindy immediately if any issues arise.
- Adjacent property: Please maintain a respectful distance from the private property located north of the apartment complex and avoid interaction with the property owner.
- Remove keys and batteries.
- Remove easily detachable parts or accessories.
- Lock all gas caps.
RFP-0010 — Contractor Q&A
Bottle Rock Harrington (CWDG-1)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
This project will include up to 100ft of roadside clearing on the Bottle Rock Road side of the parcels, and up to 300 ft on the Harrington Flat side of the parcels subject to property owner agreement.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are steep in places. Use appropriate footwear and exercise caution.
- Falling limbs: Removal of dead and dying trees is part of the project prescription. Be alert to overhead hazards during felling and limbing operations.
- Ticks: High grass and dense vegetation make this a heavy tick area.
- Road traffic: Both Bottle Rock Road and Harrington Flat Road are heavy traffic roadways. Caution should be used during all roadside work. Harrington Flat Road is home to a tight knit community. Property owners will stop and chat often.
RFP-0020 — Contractor Q&A
Bottle Rock North Roadside Clearing (CWDG-1)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are rocky and uneven in places. Use appropriate footwear and exercise caution.
- Falling limbs: Removal of dead and dying trees is part of the project prescription. Be alert to overhead hazards during felling and limbing operations.
- Ticks: Tall grasses and thick brush make the area prone to ticks.
- Traffic: Bottle Rock Road is a high traffic thoroughfare. Traffic moves quickly around sharp corners. Highly trained traffic control is a requirement on this project.
Parcels marked with a checkered pattern on the Exhibit B map are currently limited to work within the County Right of Way only. Specific scopes for each area will be reviewed with the contractor before work begins, and project maps will be provided.
RFP-0021 — Contractor Q&A
Lower Aves Phase 2 (CWDG-2)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Encampment and aggressive dogs: There is a large and established encampment on this project site. The project is supported by the City of Clearlake’s Police and Code Enforcement Departments.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are very rocky and uneven. Use appropriate footwear and exercise caution. Take care when using mechanical equipment.
- Trash: This project site contains a great deal of trash. The goal is to get the area cleared of trash prior to project implementation. CLERC will provide contractor bags for the trash, which can be left on site for collection later. Contractors are not expected to pick up hazardous materials and should coordinate with the CLERC Program Manager if hazardous materials are observed in the project area.
Nesting birds and other areas that need to remain intact will be flagged by CLERC using the following color code system: pink and red together indicates a nesting bird, and pink and yellow together indicates a wood rat nest. Do not perform any work within 10 feet of the flagged areas.
It is also important to remain aware of the flagging. Remember that if something is taken down that was flagged, the contractor is in breach of their contract with CLERC.
RFP-0016 — Contractor Q&A
Sunrise Drive Roadside Clearing (CWDG-2)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Slope instability: This project area is surrounded by cut banks.
- Lava rock: The area is covered in lava rock, which causes uneven ground and slippery conditions.
- Snakes: Rattlesnakes are abundant in this area.
- Speeding vehicles: The speed limit is 20 MPH on Sunrise Drive, which is not honored by local residents.
CLERC biologists will be conducting nesting bird surveys ahead of the contractor’s work. We do not have any botanical concerns for this project. Do not spray chips on the cut banks. Chips may need to be removed from some of the roadside areas, and CLERC can be billed for the disposal.
We have about two-thirds of the Rights of Entry for this project, and we are working on securing the rest in partnership with the HOA. Additional properties will be added to the project with contract amendments.
RFP-0022 — Contractor Q&A
Lower Aves Defensible Space Phase 3 (CWDG-2)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Encampment and aggressive dogs: There is a large and established encampment on this project site. The project is supported by the City of Clearlake’s Police and Code Enforcement Departments. There is also a fifth-wheel located on this project site that does not belong there. The Police Department has been alerted to this and the inhabitant will be relocated.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are very rocky and uneven. Use appropriate footwear and exercise caution. Take care when using mechanical equipment.
- Trash: This project site contains a great deal of trash. The goal is to get the area cleared of trash prior to project implementation. CLERC will provide contractor bags for the trash, which can be left on site for collection later. Contractors are not expected to pick up hazardous materials and should coordinate with the CLERC Program Manager if hazardous materials are observed in the project area.
Nesting birds and other areas that need to remain intact will be flagged by CLERC using the following color code system: pink and red together indicates a nesting bird and pink and yellow together indicates a wood rat nest. Do not perform any work within 10 feet of the flagged areas.
RFP-0023 — Contractor Q&A
Lower Aves Defensible Space Phase 4 (CWDG-2)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Encampment and aggressive dogs: There is a large and established encampment on this project site. The project is supported by the City of Clearlake’s Police and Code Enforcement Departments. There is also a fifth-wheel located on this project site that does not belong there. The Police Department has been alerted to this and the inhabitant will be relocated.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are very rocky and uneven. Use appropriate footwear and exercise caution. Take care when using mechanical equipment.
- Trash: This project site contains a great deal of trash. The goal is to get the area cleared of trash prior to project implementation. CLERC will provide contractor bags for the trash, which can be left on site for collection later. Contractors are not expected to pick up hazardous materials and should coordinate with the CLERC Program Manager if hazardous materials are observed in the project area.
The project area has oak woodlands, grey pines, and chaparral. Invasive species, and large, dead trees need to be removed. Dense chaparral needs to be thinned. Cleaning equipment with an air compressor before and after the work is crucial to avoid spreading seeds.
The process of securing warrants may impact the starting schedule of this project.
RFP-0024 — Contractor Q&A
Lower Aves Defensible Space Phase 5 (CWDG-2)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Encampment and aggressive dogs: There is a large and established encampment on this project site. The project is supported by the City of Clearlake’s Police and Code Enforcement Departments. There is also a fifth-wheel located on this project site that does not belong there. The Police Department has been alerted to this and the inhabitant will be relocated.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are very rocky, uneven, and slippery. Use appropriate footwear and exercise caution. Take care when using mechanical equipment.
- Trash: This project site contains a great deal of trash. The goal is to get the area cleared of trash prior to project implementation. CLERC will provide contractor bags for the trash, which can be left on site for collection later. Contractors are not expected to pick up hazardous materials and should coordinate with the CLERC Program Manager if hazardous materials are observed in the project area.
- Disposable Syringes/Needles: Do not touch any disposable syringes (AKA needles). Notify the Program Manager immediately.
- Propane tanks: The contractor will need to be aware of the potential of propane tanks in areas where a home once stood. Some of those tanks are still half full.
We don’t have as many Rights of Entry for this project – many of the homes are in tax default. The City of Clearlake will provide the initial trash cleanup before the project begins.
The process of securing warrants may impact the starting schedule of this project. We are currently ready to ask the judge to issue warrants for Phase 1 of this project.
The intent is to create a fair and consistent bidding process while allowing contractors to recover costs over the course of the project, rather than on any single property.
RFP-0025 — Contractor Q&A
Lower Aves Defensible Space Phase 6 (CWDG-2)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Encampment and aggressive dogs: There is a large and established encampment on this project site. The project is supported by the City of Clearlake’s Police and Code Enforcement Departments. There are also some aggressive dogs known to chase cars and bite tires.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are very rocky, uneven, and slippery. Use appropriate footwear and exercise caution. Take care when using mechanical equipment.
- Trash: This project site contains a great deal of trash. The goal is to get the area cleared of trash prior to project implementation. CLERC will provide contractor bags for the trash, which can be left on site for collection later. Contractors are not expected to pick up hazardous materials and should coordinate with the CLERC Program Manager if hazardous materials are observed in the project area.
- Disposable Syringes/Needles: Do not touch any disposable syringes (AKA needles). Notify the Program Manager immediately
- Hazardous Trees: Portions of the project contain dead and dying trees. These conditions increase the risk of falling limbs, unstable stems, and other hazards during tree felling and processing.
- Power Lines: The project area includes a substantial corridor of overhead electrical transmission/distribution lines.
- Cannabis Grows: If there is a cannabis grow on a vacant lot, do not approach the area. Reach out to the Program Manager and she will make arrangements with the Clearlake Police Department for its removal.
The process of securing warrants may impact the starting schedule of this project. We are currently ready to ask the judge to issue warrants for Phase 1 of this project.
RFP-0026 — Contractor Q&A
Rodde Property Defensible Space (CWDG-1)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
- Encampment and aggressive dogs: There was an established encampment on this project site on the corner between Walmart and the college. The project is supported by the City of Clearlake’s Police and Code Enforcement Departments, and they removed the encampment a month ago, but there is remaining debris that the City should be coming to clean up before the job starts.
- Heavy traffic area: There could still be people or dogs moving through the area.
- Snakes: Rattlesnakes are present in the area. Watch your step, especially around rocky terrain and debris.
- Terrain: Ground conditions are very rocky, uneven, and slippery. Use appropriate footwear and exercise caution. Take care when using mechanical equipment.
- Trash: This project site does contain trash. Contractors are not expected to pick up hazardous materials and should coordinate with the CLERC Program Manager if hazardous materials are observed in the project area.
- Disposable Syringes/Needles: Please be aware of the risk of needles in the area. Do not touch any disposable syringes (AKA needles). Notify the Program Manager immediately.
- Hazardous Trees: Portions of the project contain dead and dying trees. These conditions increase the risk of falling limbs, unstable stems, and other hazards during tree felling and processing.
- Mediterranean Oak Borer (MOB): If you detect pest infestation, CLERC should be informed. We don’t expect much of that here, but we do need to be made aware of any presence.
- Property Structural Issues: There are 4 adjoining properties with structural issues due to a previous burn.
RFP-0027 — Contractor Q&A
Riviera School Defensible Space (CWDG-1)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Proposal deadline: Friday, August 14, 2026 by 5:00 PM
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
The original project area needs to be as complete as possible before school starts on September 8th, as contractors will not be able to use school grounds as a staging area with the children present. The new parcel can be accessed from other roads, so that work can be done after school starts.
The scope will require hand work, limbing trees and removing anything under the tree driplines. There aren’t many dead or dying trees, so they can be retained as snags.
RFP-0012 — Contractor Q&A
Konocti Road Below the Gate Phase 2 (CWDG-1)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
Oaks, buckeye and redbud are to be preferred for retention but will require thinning where overcrowding occurs. To date, no Mediterranean Oak Borer has been detected in this area. Fuel ladders should be removed, and remove vegetation in the driplines of the larger trees. Remove gray pines and other small-diameter trees below 8” DBH. On the lower end of the project, thin chaparral and retain native trees and shrubs within spacing guidelines. A track chipper is preferred for this project. Chips may be spread over the leaf litter.
You will need to obtain an encroachment permit from the county for this project. If you list CLERC as the agency that you’re working with, the county will waive the fee. You’ll want to select areas to work that will not block the road as there are residents that live on the mountain as well as recreationists that want to use the public park at the top. It will be very dusty, so bring lots of water.
Note: while CLERC would prefer to maintain the 6-week timeframe from contract execution to project completion, we understand that there are extenuating circumstances that prevent this. Contractors are not expected to include overtime in this proposal. The expectation is to have the project completed by mid-November.
This work takes place in a wildland environment and is not in close proximity to residences. The primary objective is to reduce ground and ladder fuels, so there is no expectation that trees will need to be climbed.
Contractors are responsible for confirming that their license classification allows them to self-perform the work they intend to complete under this contract.
RFP-0028 — Contractor Q&A
18th/Phillips Avenues Defensible Space (CWDG-1)
Project-specific questions and answers. For contacts, site visit, invoicing, proposal scoring, and tree permits, see the General RFP FAQ.
Questions? documents@theclerc.org · (707) 261-0008 ext. 3
There is a large oak woodland on one of the parcels. The oaks need to be thinned, removing smaller diameter trees, limbing trees and removing fuel ladders. In the chaparral areas of the project, remove shrubs with the spacing indicated in the Scope of Work for this project. On the hill behind the Behavioral Health building, thin and remove vegetation.
There were no additional questions.